Examples
Background
Project launch for the production of 50 identical satellites.
Goals
Reduce costs by 50% and production cycle time by 30% (compared to
the traditional production of a single satellite) taking advantage of the
serial effect.
Proposed program
- Proposed solution allowing to define, decline and reach the costs
objectives
- Organisation of an concurrent engineering process based on the
proposed method and transfunctional teams
Results
- Design to cost method applied to all the developed equipments
- Costs targets met and cycle times reduced to 14-16 months
(compared to 24 months for traditional production)
- Complementary resulting margins allowing the company to develop
new businesses for similar satellites